Applying the start time of a specific shift to a range of other shifts.

  1. Select the shift to be used as the anchor.
  2. Then press and hold the Ctrl key whilst selecting the other shifts.
  3. Right click on any of the select shifts 
  4. Select Shift Size then Apply Start.
  5. The shifts selected now have the same start time as the anchor shift.